So, first of all, I owe you a little update and a time frame of what we’ve done til now:
- End of September 2009 – we found our land
- December 2009 – we signed all the papers and became the proud owners of 550m2 in Zgornje Škofije
- From January till December 2010 we worked with our architect on the house plans and the documentation for the building permission
- 24th December 2010 we brought all the papers (cca 20kg) to the city hall for approval
- Friday 13th May we got the permission to build
- June 2012 we received the last plans that we needed to start with the building
- November 2012 we got the loan we needed
- 3rd December 2012 the builders started to dig the cave for the foundations of the house
- April 2013 the roof was on
- May – June they put in the windows
- 1st June we got married
- Right now we are working inside the house